1.  Put dry ice pellet or nugget into the dry ice bunker in accordance with the following table and cool down for 2-4 hours before placing cargo in the container ;

Duration of carriage plus cooling-down time (Hours)
Desired Temperature
-5 C  (23 F) 0 C  (32 F) +5 C (41 F) +10 C  (50 F)
Kg. Lb. Kg. Lb. Kg. Lb. Kg. Lb.
5 16 35 15 33 14 31 13 29
10 21 46 19 42 18 40 16 35
15 26 57 24 53 23 51 21 46
20 31 68 29 64 27 60 26 57
24 35 77 34 75 32 71 30 66

2.  Put 8 pieces of new batteries ( D size / 1.5 Volt ) into the battery holders;

3.  Set temperature setting dial at required degree;

4.  Turn switch on and confirm red light illuminates before placing cargo in the container;

5.  Upon unloading cargo, turn switch off and remove all batteries from the battery holder.

1.  Put dry ice pellet or nugget into the dry ice bunker in accordance with the following table and cool down for 2-4 hours before placing cargo in the container ;

Duration of carriage plus cooling-down time (Hours)
Desired Temperature
-5 C  (23 F) 0 C  (32 F) +5 C (41 F) +10 C  (50 F)
Kg. Lb. Kg. Lb. Kg. Lb. Kg. Lb.
9 51 112 48 106 45 99 42 93
14 61 134 55 121 50 110 45 99
19 69 152 63 139 56 123 49 108
24 73 161 68 150 60 132 52 115
27 - - 73 161 64 141 54 119
29 - - - - 67 148 57 126

2.  Put 6 pieces of new batteries ( D size / 1.5 Volt ) into the battery holders;

3.  Set temperature setting dial at required degree;

4.  Turn switch on and confirm red light illuminates before placing cargo in the container;

5.  Upon unloading cargo, turn switch off and remove all batteries from the battery holder